The New Facilities Construction Committee (NFCC) has been charged with guiding the renovation of The Mountaineers new headquarters in Building 67 at Magnuson Park. Our aim is to keep you up-to-date with developments relating to the building's progress.

See photos of the building progress on our Flickr site.


Updates

April 11, 2008 - More Pictures!
Today, a ton of new pictures went up on the Flickr site. See the destruction of the shed! Roofing! Asbestos!


February 11, 2008 - New Video
Follow this video link to see Mountaineers volunteers in action, disassembling an air scrubber vent.


February 11, 2008 - On The Move
Eric Linxweiler, acting president and president-elect of the Mountaineers Board of Trustees, signed the general contract with Saltaire Construction for the remodeling of the new club headquarters. The amount is for $3,573,676. Abatement will start on Feb. 18 and substantial completion is anticipated on Sept. 9. Volunteer work parties continues to make a major contribution. Nice work and thanks!

Gene Yore, Magnuson Project Manager, for the NFCC


February 11, 2008 - News item in March 2008 Mountaineer.

Groundbreaking for a new Mountaineers home will begin on Presidents Day, Feb. 18, as a result of the recent signing of a construction contract for remodeling Building 67 in Magnuson Park. Though Mountaineers volunteers have been busy helping with some demolition work over the past couple months, Saltaire, Inc., will start the technical work of remodeling on Monday with a tentative deadline of completion set for Sept. 9. The Mountaineers are scheduled to occupy the new building in the fall.

Mountaineers Project Manager Gene Yore noted that the flexibility in the deadline is important to ensure that quality is not compromised when it comes to the building's accommodations. "We are more interested in quality than the time (factor)," he stated.

The first area of the building to undergo reconstruction will be the roof, according to Yore, in five sections, starting from north to south. The demolition of non-hazardous interior structures will follow.

The general contract with Saltaire totals just over $3.5 million. Yore noted that the "soft costs," permit fees, architectural fees, consultation fees and other preparatory work, will bring the total cost of the remodel to $4.2 million. The club's portion of that cost is $2.5 million. Goodman Real Estate, the purchaser of The Mountaineers' former headquarters in Queen Anne, Seattle, is picking up the balance of the total cost.


February 11, 2008
New images have been added to the Flickr site, including floor plans, concept art and pre-construction work party photos.


January 23, 2008
Five new photos have been added to the Flickr site.


January 15, 2008 - On the Move
Over the past month, "On the Move" at Magnuson has been synonymous with Mountaineers "volunteers at work." While progress ground to a halt for the holidays, we were able to resume Mountaineers work parties inside Building 67 during January. So far, we have had 10 work parties varying in size from 2 to 11 people. We have accumulated over 332 people hours of effort.

Saltaire Construction has been impressed with both the quality and quantity. We have developed both management and accounting methods with Saltaire to continue volunteer work through out the renovation. Saltaire will credit The Mountaineers for the value of this work. Work parties have gutted storage bins in the shed and removed the wooden beams from its face to minimize damage during demolition.

These beams are to be reused in the canopy along the front of the building. We have salvaged the shed's chain-link fence for future reuse in the lower-level storage areas. We have also made three trips to recycling, and salvaged several tons of pipe and other metals which will be sold for scrap and other purposes. The photos above show the shed before and after volunteers extracted the beams and removed apparatus from the shed's interior.

Gene Yore, Magnuson Project Manager, for the NFCC


December 14, 2007 - On the Move
Driving by Building 67 at Magnuson Park last month you may have seen a flurry of activity. Start-up work is under way for The Mountaineers new headquarters in anticipation of starting the general contract on Jan. 2. A number of significant project milestones are expected to have been completed by New Years: the final approval of the master use permit and the building permit, signing the general contract and the start of abatement.

Ten Mountaineers volunteers spent Sat., Dec. 1, carefully removing a floating floor left by Circus Contraption. This Magnuson work party salvaged about 110 sheets of plywood that will be reused during the renovation. This outstanding effort will save $3,500 and divert this plywood from a landfill. Nice work, and thanks!

The Magnuson Instructional Requirements Group (MIRG) met in December to perform a critical review of the fi nal construction drawings and plans. A few new requirements were identifi ed that had not been previously documented. We hope to accommodate these within the current scope. No deficiencies were identified.

On Dec. 10, along with Walt Reissig of MIRG, we reviewed the south climbing wall at EnterPrises in Redmond, Oregon. The wall builders are exceeding both our expectations and their proposal. The south wall was moved to a secure storage space in December to await installation in May 2008. EnterPrises is scheduled to fabricate our interior wall in February.

A move as soon as July 2008 appears achievable.


November 15, 2007 - On the Move
All major design issues in the Construction Drawings, rev3, have been resolved to the satisfaction of the NFCC. The final geo-technical report was submitted to the city last month and the master use and building permits should be issued this month.

All contract language, except guaranteed maximum price (GMP), was agreed to with Turner Construction Co. last month. However, we did not sign the general contract as anticipated. Turner?s GMP was unexpected and out of line. Turner is studying its price and may revise it and recommend value engineering alternatives. The NFCC is also getting bids from two additional fully qualified general contractors. We anticipate having a plan and proceeding next month.

Glenn Eades, the Magnuson Instructional Requirements Group co-chair, and I visited Entre Prises? factory in Redmond, Oregon, last month to review the fabrication of the South Climbing Wall. The steel frame and fiberglass skin for the left tower are complete. This defines the overhaul topography. We made a few minor modifications. We also watched the chalk stone being positioned in the left chimney. A climber can either squeeze behind it or come out on the face and climb over it. Next the climbing surface is applied. It is a composite and defines all the detail cracks, huecos and other detail features. The right tower is to be fabricated during December.

The NFCC selected Commercial Sound & Video as our audio vendor. They bid the simplest and least expensive system. It will be really simple to reconfigure and control volume for any of the various configurations of our multi-purpose rooms.

Gene Yore, NFCC


October 11, 2007 - On the Move
A 5'x16' banner "The Mountaineers, Arriving 2008!" was hung on Building 67 in early October. After nearly 2 years of planning, negotiating, designing, spec writing and much paper, this was the Mountaineers' first physical activity on site. Turner Construction started mobilization the third week of October and took about a week to secure the site, bring in construction offices, temporary power, phones, etc. Abatement of lead, asbestos, etc. should be well underway in early November and will take about a month.

The Master Use Permit and the Building Permit were delayed. The City reversed itself and required a full Geo-Tech report for the Environmental Critical Slopes on the west and south sides of the South Plaza. The resulting soil tests dictated that the hiking trail be redesigned and the south slope beefed up with more boulders and rocks to stabilize it.

Turner Construction selected the electrical contractor in October. They should have all the subs under contract by early November. Likewise the buy out of all material should be complete in early November.

Last month we met with Parks management to brief them on our grand plan. We request extending our lease to most of the lower level. We also discuss details of The Mountaineers Annual Plan which is required by our lease. They are very positive and are anxious to have us there.

Also, last month volunteers preformed several tasks for the-good-of-the-cause. Three helped Circus Contraption move so the building could be vacated 3 weeks early. Another volunteer did pre-construction power wash cleanup. Two people helped hang the banner. Thanks to John Wick, Charlie Zwick, Manlio Vecchiet, and Glenn Eades.

The most recent draft schedule shows our move during May 2006. This is more realistic. We will have the final schedule next.

Gene Yore, NFCC


September 11, 2007 - On the Move
Clark Design Group, the architect for the new headquarters at Magnuson Park, has responded to over 200 comments, corrections and changes requested through the New Facility Construction Committee's (NFCC) drawing-review process. The revisions have added several weeks to the schedule.

The contract with Turner Construction Co., the general contractor, has also taken longer than anticipated to complete. The drawing revisions and legal comments have required the additional time. A two-phase contract is now likely to allow demolition and hazardous material abatement to begin before all the updates to the plan are finished.

It is anticipated that the Master Use Permit and the building permit will be approved by the time this goes to press.

The contract with Entre Prises was signed in September for the factory fabrication and on-site installation of the climbing walls. Structural steel is on order. Fabrication of our wall for the climbing plaza will occupy most of Entre Prises' factory floor in Bend, Oregon, through the end of December.

Volunteers will play an important role in completing certain interior furnishings and other elements not included in the construction budget. Six volunteer carpenters will be needed for a week each in February. Also, a woodworker and a cabinet maker will be needed to modify existing mail boxes, selected work stations and book shelves, and build two AV-computer-friendly podiums.

In the traditional spirit of the club, volunteers have already come forward. One has volunteered to power wash areas that need pre-construction preparation for the installation of climbing facilities and nearly all of the six carpenter needed have stepped forth.

An artist with architectural illustration or sketching experience is needed to prepare plan renderings to be used in promotional materials, press releases and communications with club members, the City of Seattle and general public. Anyone who wishes to volunteer is invited to contact The Mountaineers administrative offices and leave your name, skills and availability.

Late April, 2008, remains the optimistic move-in date!

Gene Yore, NFCC


August 14, 2007 - On the Move
The Mountaineers have been planning, strategic thinking, negotiating and then doing more planning and negotiating on the renovation of Building 67 and our move to Magnuson Park for over 2 years. The NFCC is now focused on the volumes of details in the construction drawings and contract language.

We expect to sign a negotiated contract with Turner Construction Co. in earlier September. The Master Use Permit and Building Permit approvals are on a similar schedule. Seattle Parks has notified the five current tenets in Building 67 of the need to vacate in October. After securing the construction site the first activity will be abatement of lead and asbestos. The seismic upgrade to meet current code will be part of the general contract.

The recent schedule from Turner/Goodman projects our move to begin on Monday, March 17, 2008. We believe this is a very aggressive schedule. However, once we receive an occupancy permit from the City, we have 30 days to vacate 300 Third Ave. Thus, we will plan for 3/17/08 with contingencies for a possible later date. Move planning, Magnuson room schedules and storage assignments will begin this month. These will involve staff, Seattle Activities and all other building users.

Gene Yore, NFCC


July 13, 2007 - On the Move
The building plans are undergoing a cost evaluation to assure that the projected cost remains within the project budget cap. Requirements for mechanical and lighting systems have been established and design is progressing. The New Facilities Construction Committee reviewed the preliminary package of interior materials, finishes and colors and Clark Design is preparing an updated plan for review and approval.

Coordination of the building's seismic upgrade design and the structural elements needed to support the climbing facilities has taken a little longer than anticipated, in order to minimize redundant structural members and their associated costs. The climbing plaza's preliminary landscape plan is undergoing design "tweaks" to maximize the instructional capabilities of the proposed trail, inclined slabs and the boulder field.

Project construction plans are now projected to be completed about August 1 for review and approval by the NFCC.

Gene Yore, Co-Chair of the Magnuson Instructional Requirements Group, the committee that developed the program for the design of the climbing wall and plaza, been hired to represent The Mountaineers' interest in the day to day matters pertaining to project construction and administration. He will report to the Club's Executive Director.

Julian Sayers, NFCC


June 12, 2007 - On the Move
Building design and permitting processes are proceeding on schedule with the recent filing of the building permit application with the City of Seattle.

The design team and the NFCC are currently completing many of the building's details, including the library, bookstore and storage layouts, the design of the electrical, lighting, telephone, internet, utility and mechanical systems, and casework design.

Entre Prises USA has begun the design of the climbing walls in accordance with the concept developed by the Club's Magnuson Instructional Requirements Group, led by Gene Yore and Glenn Eades.

The outdoor wall will be a freeform facility, built in a twin spire configuration, joined by a bouldering-height middle section. Each spire will be unique and address different degrees of difficulty, though each will have full height chimneys, cracks and other features that will facilitate climbing without using the bolt-on holds. The wall, which will receive a custom paint scheme, will include a multitude of anchors and bolt-on hold locations for added variety and instructional flexibility.

The indoor wall will be a combination of freeform and imprinted panels, which will feature chimneys, cracks, pockets, slabs and ledges. It will also include many anchors and bolt-on holds.

Building plans are expected to be completed during the first week of July.

Julian Sayers, NFCC


May 11, 2007 - On the Move
The construction plans for the Club's new building at Magnuson Park are 85% complete, as of May 10. Landscape design, including the climbing plaza and the front entry, is progressing with close coordination by the landscape architect with the architect, the New Facility Construction Committee, the Naturalist Committee and the Magnuson Instructional Requirements Group. Indigenous species of trees, shrubs and groundcover will be integrated with the facility requirements for climbing, MOFA, scrambling and other Mountaineer instructional programs.

The design of the climbing wall by Entre' Prises USA, is well underway and is projected to be finalized, together with the landscape plan, by mid June. The basic storage room and locker layout is being incorporated into the building plans in accordance with identified program needs. In the coming months, these facilities will need additional input from the various user groups regarding the need for shelving, racks and other elements in each assigned space.

Over the next several weeks, much of the design effort will be spent on building infrastructure such as utilities, heating and ventilation systems, lighting, security, structural engineering review, ADA stair and equipment lifts, and electrical, telephone and computer systems. Casework, library and bookshop shelving and interior finishes and materials will also be addressed during this period.

The permit package is projected to be filed with the City of Seattle during the first week of June to initiate the official review.

The first building walk-through, hosted by Past President Glenn Eades at the site, was held on Saturday, May 12. Monthly project status reports are included in the Seattle Branch Council meetings at the Seattle Clubhouse on the third Thursday of each month at 7:00 p.m. Look for additional presentation and comment opportunities on the Club's website when a complete building, climbing wall and landscape plan set is available.

Julian Sayers, NFCC


April 12, 2007 - On the Move
Work on the Club's Magnuson Park facility is progressing on several fronts. Project architect Clark Design Group, PLLC, has incorporated the New Facility Construction Committee's requested revisions in the preliminary building plans and is awaiting a building code interpretation from city officials regarding unique mezzanine and storage issues, so the plans can be finalized. Plan review is underway by Entrix, the City's Magnuson Park consultant, to assure compliance with the Sand Point Historic Properties Reuse and Protection Plan. A landscape architect will soon be added to the design team. The Club's Naturalist Committee and its Instructional Requirements Group will provide consultation on site design features including the entrance and climbing plazas. The evaluation of interior furnishing needs has begun. Project Manager Kelli Norris is completing a master schedule in coordination with the various firms who will be involved in project construction.

After a thorough evaluation of the Club's instructional needs and qualified vendors by the Instructional Requirements Group, Entre-Prises USA, Inc. of Bend, OR, has been selected to design and construct the new climbing facilities.

Best known locally for the climbing structures at REI and the University of Washington, the firm has 20 years experience and over 3500 structures, worldwide, in its resume.

Planning is underway for a series of meetings, including guided building tours, to review plans with Club members and to introduce the plans and programs to community groups. Plan illustrations and an event schedule will be prepared after the initial code, pre-application and historic reviews have been completed. When available, these materials will also be posted on the Club's website.

Julian Sayers, NFCC


March 29, 2007 - Article in The Mountaineer
Building sale finalized; club to move in '08
By Brad Stracener, Managing Editor of The Mountaineer

The Mountaineers Board of Trustees has ratified the purchase and sale agreement to sell the club headquarters building and relocate to Magnuson Park.

The deal closed on March 2, according to Executive Director Steve Costie, but the architect, Clark Design Group, PLLC, had been working on the design of the new building months before the sale of the current building closed. Construction is expected to begin before the end of the year, according to Costie, and the club should be able to move into its new home some time next year.

Read the entire article here.


March 13, 2007 - On the Move
The sale of The Mountaineers Building to Goodman Real Estate, Inc. for $4,500,000 closed on March 2, 2007. Terms of the sale include Goodman's guarantee of the tenant improvement costs that exceed $2,500,000 and the assumption of project management responsibilities for the design, permitting and construction of the Magnuson Park improvements at no cost to the Club, but with its active participation.

Kelli Norris, a highly regarded Goodman manager, has been designated Project Manager and The Mountaineers' New Facilities Construction Committee will continue in its role of overseeing the building renovation on behalf of the Club.

The Climbing Standards Committee, which recently drafted specifications for the desired instructional facilities, is nearing the completion of its evaluation of special contractors, one of which will be retained to design and construct the climbing plaza wall, as well as indoor facilities and additions to the north facade.

Clark Design Group PLLC, the project architect, is completing refinements to the preliminary building plans requested by the NFCC. When ready, these plans and samples of materials and finishes will be presented for review at meetings, to be scheduled, for the Club's user groups. Ms. Norris' work currently includes cost control and critical path task scheduling.

Julian Sayers, NFCC


February 14, 2007 - On the Move
The Mountaineers New Facilities Construction Committee has reached agreement on a final building plan concept, general scope of work and club budget for the building renovation at Magnuson Park. A summary of the package was presented to the Board of Trustees at its February 1 meeting by the NFCC and representatives of John Goodman Real Estate, Inc., the purchaser of the club's current building. The agreement will cap the club's construction cost risk by providing for Goodman's absorption of the costs over $2.5 million, a contribution projected to exceed $500,000. This will enable the club to establish an endowment fund with the sale proceeds not used for the club's share of the construction costs, to assure that the long-term club facility needs will be met well beyond the 30-40 year term of the park lease.

Clark Design Group, PLLC, the project architect has offered to donate the effort needed to pursue a silver LEED (environmentally green) building status.

The building will present a rugged outdoor image, emphasizing the use of the concrete and heavy timber construction. The exterior is planned to include a broad array of climbing, scrambling, MOFA and other teaching facilities in a plaza adjacent to the south wall, as well as anchors on the north wall. Interior spaces will feature flexible assembly areas, some with movable sound-insulated partitions, that will accommodate 5 to 8 simultaneous events of 8 to over 500 people. An attractive entry lobby, member services-bookshop area, library, administrative offices and activity storage facilities are also included.

The project can now move on to address scheduling, the preparation of refined plan illustrations for presentation to club user groups, and detailed plans and specifications for permits and construction. As these and many other tasks are completed, key items, benchmark dates and status reports will be posted on the club's website. Building completion and move-in is projected for late spring, 2008, after the club's winter-early spring peak course period is completed.

Julian Sayers, NFCC


September 15, 2006 - On the Move
A major benchmark toward the realization of the club's new headquarters building at Magnuson Park was achieved this month with the selection of The Clark Design Group PLLC as the architect and Rafn as the general contractor.

Letters of intent have been signed with both firms that direct the preparation of detailed contracts.

Clark and Rafn have exceptional project résumés that include many historic renovations and work for non-profit clients on limited budgets. Clark, led by principal Scott Clark and project architect Jason Land, has offered to donate extra services to assure that the facility will meet a "green building" standard, appropriate to the club's environmental conscience. Rafn, a respected Seattle general contractor for many years, will involve senior personnel with relevant experience to the project in management and supervisory roles, including Steve Stroming, Mike Harnden and Ann Schuessler. The renovation of the historic Cadillac Hotel in Pioneer Square, which now houses the National Park Service's Klondike Gold Rush Museum, is a recent Rafn project. The company is particularly capable in assisting architects in the design process and in the important areas of quality and cost controls.

Entre-Prises, a nationally acclaimed climbing wall builder, is the leading candidate for the climbing plaza. The club's climbing wall advisory team, led by Gene Yore and the project architect, will tour the firm's NW projects in October, prior to confirming this key project sub-contractor as a design-build team member.

Clark Design Group and The Mountaineers Books Division are currently evaluating office plan alternatives for the lower level of the Magnuson Park building. The NFCC (New Facilities Construction Committee) will soon begin the process, with the Seattle Parks Department, of expanding the scope of the lease agreement to include the additional space for the Books Division's offices.

Submitted by Julian Sayers, NFCC


August 10, 2006 - On the Move
Preliminary estimates indicate that The Mountaineers Books Division could achieve a significant annual savings, after its current lease expires in 2008, by relocating its offices to the new Club facility at Magnuson Park. The Division's staff and the New Facility Construction Committee (NFCC) are working to perfect a program of Books' space needs and a more definitive estimate of the cost of a potential move so that a reasoned decision can be made.

The timing of the architect-general contractor team selection has been extended into September so that consideration of a potential Books Division phase can be incorporated as an option in the scope of work.

Current schedule projections indicate that occupancy of the new quarters can be expected about mid spring, 2008. With the objective of avoiding a move during the Club's peak late winter-early spring course period, occupancy after, rather than before, this busy period should eliminate the threat of overtime construction costs that could be required to rush building completion by late fall, 2007.

Submitted by Julian Sayers, NFCC


July 14, 2006 - On the Move
All architect-contractor design team candidates for the new facility at Magnuson Park have now been interviewed by the club's New Facility Construction Committee (NFCC). A decision on team selection is expected toward the end of July after the Committee completes its evaluation of several design alternatives that emerged in the course of the interviews. Upon hiring the design team, work will begin immediately, with top priorities given to firming up the building design, the project cost estimate and the schedule.

****

A climbing wall and plaza design advisory committee has been established, under the leadership of Gene Yore and Glenn Eades, to assist the NFCC with this unique element at the new site. The committee, which is comprised of club members having special expertise in climbing, scrambling and MOFA instruction, has examined climbing facilities in various regions of the country in order to take advantage of the experience of others.

Meetings with Seattle city officials have been held to identify the scope and likely schedule of the required permitting process.

Submitted by Julian Sayers, NFCC


June 9, 2006 - On the Move
The New Facility Construction Committee (NFCC) has begun the process of selecting a general contractor and design team. The project will employ the "design-build" method, a concept in which the prime contractor also plays a major role in the design phase to implement the clients building program. This method has become increasingly popular in the private sector as a means of simplifying the design process, expediting design, permit and construction schedules and tightly controlling total project costs. After receiving proposals from a short list of project team candidates and conducting a final round of interviews, the Committee expects to make its selection by early July.

Steve Costie, the Executive Director of The Mountaineers and member of the NFCC, will serve as Project Manager. In this capacity, he will function as the liaison between the project design-build team and the various elements of the club, including the NFCC and the BoT, and oversee the day to day activities, as needed, with staff and NFCC assistance.

Project Timeline
Below, we've given you some rough milestones in the process of moving to Magnuson Park. As with anything, this timeline is subject to change, but it does provide a rough guide to the next year and a half.
Early July - Selection of design team
September '06 - Lease signing with Mayor of Seattle
Early Winter '06 - Final approval of architectural plans
February '07 - Groundbreaking
October '07 - Club moves in to renovated Building 67


May 9, 2006 - On the Move
The Mountaineers Board of Trustees approved moving the club headquarters to Magnuson Park's Building 67 at its April meeting.

Now that this has been decided, the New Facilities Construction Committee (NFCC) will begin the process of renovating Building 67. This means finding an architect, hiring the contractor to build/renovate, and guiding the effort to give the club the best facility for its needs.

Over the next year, we'll document the progess at Magnuson Park through this section, "On the Move." From start to finish, you'll read about the major developments, see the new building take shape and follow as we move into the new structure.


April 6, 2006
At the April 6 meeting of The Mountaineers Board of Trustees, the group voted on two important issues facing the club. On the agenda were the approval of a lease with the City of Seattle for the Building 67 property at Magnuson Park, and the sale of The Mountaineers Building.

The board voted 13 to 7 in favor of approving the lease with the City of Seattle. In a separate motion, the board then approved the sale of the building by a vote of 16 to 4. These votes came one year after the Building Advisory Committee submitted their recommendations to the board.



Links

Building Advisory Committee (BAC) website - The Board of Trustees' decisions to approve the sale of the building and to accept the lease at Magnuson Park were based on the work of the BAC. Although it is no longer active, you can visit its website to follow the history of the project.